UNE Robb College - Upgrade of Student Rooms

Project Management / Planning

Client Information

Client
University of New England
Duration
2023–ongoing, across 6 stages
Location
Robb College, University of New England, Armidale Campus
Services

o Design Coordination

o Stakeholder Engagement

o Compliance Upgrades

o Staged delivery

o "Proof of Concept" Trial

The University of New England’s Robb College houses over 275 live-in students on the Armidale Campus. The College consists primarily of single-occupancy rooms with shared facilities for both male and female students, with a small number of larger Resident Leader rooms with living rooms, private ensuites and kitchenettes.

The existing structure and fit-out of the College date from the mid-1970s. Whilst some of the common areas and fire safety systems had been upgraded over the years, the residents’ rooms were unrenovated and very much showing their age.

Given the era of the building’s design and construction, significant challenges around non-compliant electrical infrastructure and known asbestos-containing materials were present. This included both bonded asbestos to walls and ceilings and, the far more challenging to manage, friable asbestos lagging to the hydronic heater systems. Another challenge was that the bulk of disruptive works had to be constructed during the period between October and January each year when students were not in residence. However, during this period other temporary occupants, for conferences, block study for online students and school excursions to the region, need to be accommodated.

Monteath & Powys was engaged in late 2023 to work with the University’s Estate and the Built Environment Department, on the planning, design, development, procurement and delivery of an initial “proof of concept” trial of 11 resident rooms and a second trial of 9 rooms. The design was reviewed at the completion of each trial and minor changes of design were incorporated prior to the initiation of two further stages of 134 and 62 rooms. The final stage, some 60 rooms, is on track for commencement in 2026 and completion in early 2027.